Carowinds' Official Statement: Fury 325

August 10, 2023

August 10, 2023

Carowinds today announced that Fury 325 has reopened following the completion of the repair and testing process, and a final inspection by the North Carolina Department of Labor's Elevator and Amusement Device Bureau (the Bureau). The return to operation marks the end of a comprehensive plan dedicated to ensuring the safety and operational readiness of the coaster.

Over the past several weeks, crews installed a new steel column fabricated by Bolliger & Mabillard (B&M), the ride manufacturer, ensuring precise alignment and fastening of the track/column connection. Working closely with B&M and our consultants, the team initiated a series of detailed tests to ensure the coaster's safety and integrity. These included an accelerometer test that uses sensors to measure any variation in the ride experience. After that, we operated the ride for 500+ full cycles, performing tests and inspections to ensure the ride’s integrity throughout that period. B&M and a third-party testing firm then conducted a final inspection to ensure the ride surpassed all required specifications.

Earlier today, August 10, the Bureau conducted a final inspection and formally approved reopening of the ride.

We extend our sincere thanks to all those who worked tirelessly over the past few weeks to repair and prepare Fury 325 for reopening. We are excited to welcome back our guests to one of Carowinds’ most popular rides.

 

July 27, 2023

Carowinds continues to conduct a comprehensive series of detailed tests and inspections in preparation for the reopening of Fury 325. Each step of the process is under careful monitoring, with remedial action taken to ensure the structure's safety and integrity. Upon completion of this phase, the ride will undergo final inspections by the ride manufacturer, a third-party testing firm, and the North Carolina Department of Labor's Elevator and Amusement Device Bureau, all aimed at preparing Fury 325 for its reopening.

We are conducting a full maintenance review of Fury 325 during this testing process. This maintenance review – which is consistent with routine off-season procedures – includes a review of the steel superstructure, the trains, and the ride control system. During such reviews, it is not uncommon to discover slight weld indications in various locations of a steel superstructure. It is important to note that these indications do not compromise the structural integrity or safety of the ride. When such indications are found, we conduct non-destructive testing to determine the appropriate remedy. Once a repair is completed, it undergoes inspection and approval before the ride is deemed operational. Additionally, as is customary, we conduct test cycles to ensure its smooth operation before guests are allowed on the ride.

 

July 12, 2023

Carowinds is currently in the process of removing the existing support column and replacing it with a new steel column fabricated by Bolliger & Mabillard (B&M), the ride manufacturer. This replacement requires meticulous preparation and detailed execution.

This afternoon, on July 12, cranes will be assembled to securely hold and position the track element of the coaster while removing the components of the existing column. Hydraulic jacks will assist in lifting the column out of its foundation. Once successfully removed, the column will be carefully transported to a secured backstage area of the park. Grout pockets will undergo thorough cleaning to prepare for the installation of the new column.

On Thursday, July 13, the new support column, along with hardware from B&M, will be delivered. Our skilled associates will diligently install the column, ensuring precise alignment and securely fastening the track/column connection. Following the completion of the column installation, an as-built survey will be conducted to accurately determine the elevations of the base plate.

Every step of the process, from material delivery to installation, will be carefully monitored and adjusted as necessary to uphold the integrity of the structure. Carowinds is fully committed to ensuring a seamless transition and maintaining the highest standards of safety and precision throughout the project.

Once the installation is complete, as part of our standard safety protocol, a comprehensive series of tests will be conducted to ensure the coaster's safety and integrity. These will include an accelerometer test that uses sensors to measure any variation in the ride experience. After that, we plan to operate the ride for 500 full cycles, performing tests and inspections of the entire ride throughout that period. Once this phase is completed, we will ask B&M and the third-party testing firm to perform a final inspection to ensure the ride exceeds all required specifications.

Subsequently, we will collaborate with the North Carolina Department of Labor's Elevator and Amusement Device Bureau to prepare Fury 325 for reopening. We will provide an update regarding the reopening date of the ride once it has been finalized.”

 

July 6, 2023

Since July 1, the park’s maintenance team and representatives from the ride’s manufacturer, Bolliger & Mabillard Consulting Engineers Inc. (B&M), have conducted a thorough inspection of the entire track, support columns and foundation. In addition, and in partnership with B&M, we have performed a battery of tests to identify the cause of the fracture, which appears to have formed along a weld line in the steel column.

Working in close coordination with B&M, we are planning to remove and replace the existing support column. The new support column, which is being fabricated by B&M, is expected to be delivered to the park next week.

Following the installation of the new column, and as part of our normal protocol for rides such as Fury 325, we will conduct an extensive series of tests to ensure the safety and integrity of the coaster. These will include an accelerometer test that uses sensors to measure any variation in the ride experience. After that, we plan to operate the ride for 500 full cycles, performing tests and inspections of the entire ride throughout that period. Once this phase is completed, we will ask B&M and the third-party testing firm to perform a final inspection to ensure the ride exceeds all required specifications.

B&M is regarded as one of the premier ride manufacturers in the world, with an impeccable reputation for quality and engineering. It’s important to understand that rides like Fury 325 are designed with redundancies in place to ensure the safety of guests in the event of an issue such as this.

While we regularly inspect the coaster, we are planning to implement additional inspection procedures to ensure we are making every effort to promptly identify and address future potential issues. These new measures will include the regular use of drones outfitted with cameras to access and inspect hard-to-reach areas.

The safety of our guests and associates will always be Carowinds’ top priority. Once the new support column is in place and all testing and inspections have been completed, we will work with the North Carolina Department of Labor’s Elevator and Amusement Device Bureau to prepare Fury 325 for reopening. We will share an update on the reopening of the ride when a date has been finalized.