The Foundations of Copperhead Strike

Scott Gerbereux

Digital Marketing Manager

As we introduce Copperhead Strike, here's a look behind the construction fence at what’s already been set in stone – well, reinforced concrete.

The drilling company that created the foundations for Intimidator is back to perform the excavation work for Copperhead Strike. They began digging on June 4 and are scheduled to complete their portion of the project in October. 

Caissons (also called “piers”) are created by auguring a deep hole into the ground, and then filling it with concrete. A drilled pier is a deep foundation system, more commonly referred to as “footers," that is constructed by placing concrete and reinforcing steel into a shaft.

Shafts between 15' - 20' in depth are made while temporary steel casings are used to maintain the sides of the drilled excavation. Three drill rigs are digging caissons for Copperhead Strike, supported by two cranes to move drill bits to the rigs:

copperhead strike construction

Approximately 240 caisson holes will be dug for this project. A caisson is designed to rest on an underlying stratum of rock. Carowinds sits above a shelf of granite that spans the entire park. In some parts, this layer of bedrock is as close as 8 feet from the surface. A rock auger bit, pictured below, is used to cut through the granite. Cages protect poured foundation holes and caps cover exposed reinforcing bars (rebar):

copperhead strike construction

Rebar is inserted into and runs the full length of the hole and then concrete is poured into the caisson. When the concrete sets and hardens around the bars, we get a new composite material, reinforced concrete, which works well in either tension or compression - important for handling the positive and negative gravitational forces created by a roller coaster:

copperhead strike construction

It takes concrete about 28 days to reach its full strength and hardness. Cylinders of concrete from every truck are collected and the compressive strength is tested at 7, 14 and 28-day intervals. The inspection of concrete is essential to check for defects that may require repair.

Once caissons are filled with concrete and rebar, the ground around the shaft is excavated into a square and then more concrete is poured to form a "mud mat":

copperhead strike construction

This concrete layer provides a good work area to keep the rebar and formwork clean while preparing to construct a pier cap:

copperhead strike construction

Anchor bolts, which will eventually secure track supports to the pier cap, are precisely positioned. Two surveyors inspect their orientation prior to being secured in reinforced concrete. Once the concrete sets, the anchor bolts' location in the pier cap are checked for a third time. If done correctly, the slots in the track supports will fit over the anchor bolts like a Lego set:

The first two shipments of track supports arrived on August 7 and were transported to the laydown yard - an area outside the worksite where materials are stored until they are needed: 

copperhead strike construction


Most of the work to date has taken place below ground level. We are going vertical in late September, when track supports are secured to the anchor bolts. Over the coming months, there will be so much progress to share. Follow along for more inside looks at the Carolinas' first double launch coaster - COPPERHEAD STRIKE!

Share This

Scott Gerbereux

Digital Marketing Manager

Post a Comment

Skip to Next Section

Test Title

Inside Look at New Carowinds Hotel: Your Room is Almost Ready!

Here's an inside look at the in-progress model room inside SpringHill Suites by Marriott at Carowinds. These clean, modern, and spacious suites were designed for the whole family. The living and sleeping areas are built with comfort and convenience in mind.
Read More

Afterburn Turns 20!

One of Carowinds’ 14 roller coasters reaches a major milestone this year! Afterburn, widely regarded by coaster enthusiasts as one of the best inverted coasters in existence, is celebrating its 20th birthday in 2019.
Read More

Five New Shows Debut at Carowinds

This season, Carowinds has debuted FIVE new shows (including four debuting over this past Memorial Day weekend) that are performed in locations around the park and are a great complement to Carowinds’ outstanding ride and attraction portfolio.
Read More

New Carowinds Hotel - Spring 2019 Update

There's almost as much excitement surrounding the opening of Carowinds' first on-site hotel as there is for Copperhead Strike, the latest addition to our outstanding coaster lineup. Here's the latest update on construction and a peek at what the new hotel will look like.
Read More

A Brew With a Bite

A new coaster deserves a new way to celebrate and what could be better than a crisp, cold IPA? Carowinds and Sycamore Brewing have teamed together to create Copperhead Strike IPA, brewed just in time for opening day.
Read More

Double the Launch, Double the Fun!

If you’ve never experienced a launch coaster before, you’re in for a real treat. This spring, Carowinds will open Copperhead Strike, which holds the honor of being the Carolinas’ first double launch coaster. If you’re unfamiliar with the term “double launch,” don’t worry, it’s not as intimidating as it sounds.
Read More

The Making of a New Restaurant: Blue Ridge Country Kitchen

The food at Blue Ridge Country Kitchen will be so good it'll make you slap your knee and holler. I can guarantee this, because I've been fortunate enough to wander by the test kitchen while the recipes were being perfected and was an eager taste tester. Although great food is the key ingredient for a successful restaurant, recipe development is just one of the many things that go into creating one. 
Read More

January Copperhead Strike Construction Update

You ask, we answer. Here's the latest on Copperhead Strike. Construction crews are busy in the new year. 
Read More

MOST POPULAR RIDES AND ATTRACTIONS: 2018

It's just the beginning of the new year, and the park is already buzzing as we get within striking distance of the 2019 season. Before we launch into another year of thrills and family fun with our Opening Day on March 23, let’s take a look back at last season’s most popular rides and attractions. Here’s a list of Carowinds attractions that gave the most rides in 2018. 
Read More

North Pole Excursion

Take a trip to Santa's headquarters in North Pole Excursion, NEW at WinterFest! This area of the park is filled with holiday cheer and plenty of opportunities to make family memories. Here's your guide to our newest winter wonderland:
Read More